KPSD Wastewater Plant Upgrades

In our series of earlier newsletters on the plant upgrades, the District included potential amounts of increases which our customers would possibly see on their sewer billings. This is an estimated amount based on the current number of users of the system and the potential amount of the loans for which they District must apply to complete the project.
The full costs of the Project are estimated to be $32,000,000. The District currently anticipates the receipt of Leading Idaho Funding (LIF) grant funds in the estimated amount of $13,771,044. The District anticipates utilizing a bond or loan to finance the remaining project costs of approximately $18,228,956. The District is eligible for a State Revolving Fund Loan through the Department of Environmental Quality (DEQ) in the amount of $8,798,956 at a very reasonable interest rate with a repayment period of 30 years.
The District is looking at a phased approach to the revenue bond amounts to be collected with the monthly sewer charges. The increase would be phased over a period of 2-3 years to allow our patrons time to adjust for the increase more easily. The Board chose to institute only a small increase this year to begin collecting the funds for the loan repayments. The funds are specific to the loan repayment and will be moved to a specific account reserved for that purpose. Currently, the interest earning rate for the funds the District has in place with the Local Government Investment Pool (LGIP) is at 5.18% as of July 2024. Rates have fluctuated from 5.17%-5.44% for the months of January 2024– July 2024. The Board is hoping to take advantage of the current higher earning rates by reserving funds while interest rates are higher. The interest earned will be reserved for payments on the loan(s).
This year, along with the increase in the quarterly sewer amount, you will see an additional line item for the plant upgrade fee. The Board posted along with the rate increase a $3.00 per month per ER (equivalent Residence Use). This line item is specific to the plant upgrades. Please note that it is per month and per ER. This will affect those users who are metered on their sewer usage. Single Family Residences will see a flat rate of $3.00 per month on their sewer billing. This means that the quarterly statements will show an amount of $9.00 per quarter on the line item for single family residences.
The District is still pursuing other grant opportunities to help reduce the amount needed to borrow. Although additional grants have not yet been awarded, the District is still actively looking for those opportunities.
You May Also Like...
NOTICE OF PUBLIC HEARING
NOTICE OF PUBLIC HEARING Kootenai-Ponderay Sewer District The Kootenai-Ponderay Sewer District’s governing board will conduct a Public Hearing on Monday, August 24th, 2026, in the meeting room at 511 Whiskey Jack Road at 5:00 p.m. in conjunction with the annual Budget…
read moreA BETTER WAY TO PAY IS COMING JULY 28, 2026
We're excited to announce a new, online payment portal! You will still enjoy the same high-level security you expect from us, along with new features including: • Easy enrollment in Auto Pay, E-billing, and Text-n-Pay • Historical bill and payment data • Multilingual…
read more